BLOG DETAILS
The Maharashtra Housing and Area Development Authority (MHADA), acting as the designated Planning Authority under the Pradhan Mantri Awas Yojana (PMAY), has issued an Intimation of Approval (IOA) for a large-scale affordable housing project in Pune district.
The approval has been granted to M/s Deshmukh Development for the proposed construction of 407 residential tenements and 20 commercial shops under the Affordable Housing in Partnership (AHP) – PPP model of the PMAY scheme.
Land Gut Nos.: 215, 216 (Part), 217
Village: Boripardhi
Taluka: Daund
District: Pune, Maharashtra
Total Tenements: 387
339 EWS (Economically Weaker Section) units
48 LIG (Lower Income Group) units
Commercial Shops: 20
Buildings Proposed:
Building A: Stilt + 12 floors
Building B: Ground + 5 floors
Building C: Ground + 6 floors
Total Construction Area: 19,976.04 sq. m
(Below 20,000 sq. m – Environmental Clearance not mandatory unless area increases)
Project approved under PMAY-U (Urban)
Model: Vertical AHP – Public Private Partnership (PPP)
Governed by MRTP Act, 1966 and Unified DCPR
MAHA RERA registration is mandatory
PMAY housing projects have been granted an extension up to 31 December 2025
The developer must complete construction on or before 31-12-2025
Construction cannot start until Commencement Certificate (Plinth level) is issued
Multiple NOCs required, including:
Fire (CFO)
Water Supply
Drainage
Electricity (MSEB)
Airport Authority (if applicable)
Railways / NHAI / Irrigation Department (if applicable)
STP, Rainwater Harvesting, Solar Systems, Grey Water Recycling mandatory
Security Deposit: ₹1,20,015
Structural designs must be approved by IIT / VJTI / VNIT / COEP or equivalent Govt. institute
MHADA has clarified that:
The IOA is issued only for obtaining statutory NOCs
It does not permit commencement of construction
MHADA reserves the right to withdraw or cancel approval if conditions are violated or documents are found misleading